Planning pipeline · data as of 18 Oct 2026

Scotland’s Data Centre Map and Tracker

Large data centre proposals in Scotland, from pre-application notices to live planning applications and appeals, plus the sites already operating. Each entry shows its council planning record, where one exists, and its other sources by type, so every claim can be checked against more than one publisher.

How sources are graded: 37 of 47 entries corroborated ↓
  • Scottish ParliamentMoratorium on planning applications for all hyperscale data centresUnder committee considerationRead and respond ↗
  • Comment deadline Chapelcross 1GW campus22 days left · closes 15 Nov Comment on the application ↗Scheme details
  • Parliament inquiry Holyrood inquiry into hyperscale data centres22 days left · closes 15 Nov Find out more ↗
  • PetitionSave the Lammermuirs: stop the data centre 48,812 signatures of 50,000 Read or sign ↗Southside, Longformacus
  • PetitionStop the proposed AI data centre near Auchtertool, Fife 10,817 signatures of 15,000 Read or sign ↗Auchtertool

Petitions do not lodge official objections; only comments on a planning application count in the council's decision.

Sites
AberdeenEdinburghGlasgowInvernessDundeeDumfries Chapelcross (CX Technology Campus) · 1,000MW · Application lodgedi3 Industrial Park, Irvine · 1,000MW · StalledEdzell grid connection · 800MW · Grid queue onlyAuchtertool (Stoic Cato) · 600MW · Application lodgedBlackdog · 600MW · AnnouncedKillellan, Dunoon · 600MW · StalledHurlford (Stoic Rufus) · 540MW · Pre-applicationPlains (Drumshangie) · 500MW · Pre-applicationEasterhouse grid connection · 500MW · Grid queue onlyNorth Lanrigg Farm (Stoic Aurelius) · 400MW · Pre-applicationClydebridge grid connection · 360MW · Grid queue onlyGlenbervie, Larbert · 300MW · Application lodgedStainrigg Mains, Coldstream · 300MW · Pre-applicationWesterhill, Bishopbriggs · 300MW · Pre-applicationRavenscraig West · 275MW · Pre-applicationRavenscraig East · 275MW · Pre-applicationFreeport West Lothian · 250MW · Pre-applicationSouthside Data Centre, Longformacus · 225MW · Pre-applicationSouth Gyle (former RBS HQ) · 212MW · Refused / appealWester Hermiston · 200MW · Pre-applicationCreoch Farm, Ochiltree · 200MW · Pre-applicationCockenzie (former coal store) · 200MW · AnnouncedInchinan grid connection · 180MW · Grid queue onlyJawcraig grid connection · 180MW · Grid queue onlyFormer IBM site, Spango Valley · 150MW · Application lodgedDataVita DV4, Lancaster Road · 120MW · Application lodgedDataVita DV1 · 24MW · OperatingPulsant SC-1, South Gyle · 3.4MW · OperatingPulsant SC-2, Bankhead Medway · 2.16MW · OperatingBrightsolid Aberdeen · 2MW · OperatingBrightsolid Dundee · 1.5MW · OperatingPulsant SC-3, Newbridge · 1.3MW · OperatingDataVita DV2, Bothwell Street · 1MW · Operatingiomart Glasgow DC1 · 1MW · OperatingDataVita DV3 · MW not published · Under constructionDataVita DV6, South Lanridge Farm · MW not published · Pre-applicationHaspielaw · MW not published · Pre-applicationHunterston Estate · MW not published · Pre-applicationWest Barns Mains, Dunbar · MW not published · Pre-applicationDataVita Fortis · MW not published · OperatingAtos / Asanti Livingston · MW not published · OperatingAsanti Hamilton · MW not published · OperatingIFB Union Street · MW not published · OperatingLumen Glasgow · MW not published · OperatingNatWest E4 data centre, Macmerry · MW not published · OperatingRBS data centre, Melville Gate · MW not published · OperatingAdvanced Computing Facility (EPCC) · MW not published · Operating
OperatingUnder constructionApplication lodgedRefused / appealPre-applicationAnnouncedGrid queue onlyStalled

Circle area scales with MW. Hollow rings have no published capacity. Positions are approximate (town or estate level).

How sizes are banded

There is no single industry standard: sources put "hyperscale" anywhere from 10 MW to over 100 MW. This tracker uses five bands by IT or grid capacity, with Scotland's 50 MW planning threshold as the line between medium and large. DC BLOX · RISE · Scottish Government

BandCapacityProposedOperatingWhat it means
Smallunder 5 MW07Server rooms, edge sites and small colocation halls. Most of Scotland's operating data centres.
Medium5 to 49 MW01Large colocation or enterprise sites, such as DataVita DV1 (24 MW). Below Scotland's 50 MW threshold.
Large50 to 249 MW90Hyperscale scale. At 50 MW and above, councils must notify Ministers and an EIA is mandatory.
Very large250 to 999 MW150Multi-building hyperscale or AI campuses.
Gigawatt1,000 MW and above20Gigawatt-scale AI campuses, each a quarter of Scotland's winter peak demand or more.
Size unknownnot published58No capacity figure published yet.

For scale: Scotland's winter peak electricity demand is about 4,000 MW. The Register

What a megawatt means in homes

Data centres run day and night all year. 1 MW used at full capacity for a year is 8,760 MWh. Scottish homes used 8.8 TWh of electricity in 2024 across 2.57 million households, about 3,420 kWh per home. So each megawatt at full capacity is roughly the electricity of 2,560 homes. Scotland's total electricity use in 2024 was 21.7 TWh.

Sites rarely run at full capacity all the time, so pages show a range. The low end assumes three-quarters of capacity on average. That is what the two Scottish developers' figures we have imply: Auchtertool's energy statement gives 4,000 GWh a year for 600 MW (76%), and Chapelcross is estimated at 7 TWh a year for 1,000 MW (80%). Where a figure has been published for a site, its page uses that figure instead. Scottish Parliament (SPICe) Scottish Parliament

CapacityHomes' worth of electricityShare of Scotland's homesShare of all Scottish electricityCompared with every electric train in Britain
50 MW96,000 – 130,0004–5%2%8–11%
120 MW230,000 – 310,0009–12%4–5%19–26%
300 MW580,000 – 770,00022–30%9–12%48–64%
600 MW1.15 million – 1.53 million45–60%18–24%about the same
1,000 MW1.92 million – 2.56 million75–100%30–40%1.6–2.1 times

Other ways to picture it

Electricity userPer year
Every home in Scotland (2024)8.8 TWh
Every business, factory and public building in Scotland (2024)12.9 TWh
Every electric train in Great Britain, passenger and freight (2024-25)4.1 TWh
All of Scotland (2024)21.7 TWh

For balance: Scotland generated 51.8 TWh in 2024, more than twice the 21.7 TWh it used, and in 2025 about 8.8 TWh of wind in northern Scotland was switched off because the grid could not carry it. Developers argue data centres could use power that is now wasted. Whether a site would depends on where it connects: most switched-off wind is in the north, most proposals are in the Central Belt, and data centres need power on calm days too. Scottish Government The Energyst (Montel analysis)

So a 600 MW campus would use about as much electricity as every electric train in Britain. Office of Rail and Road · Scottish Government

Two things can push real use above these figures: some published capacities cover only the computers, with cooling on top, and campuses may grow beyond their first phase. Large sites are also built in phases, so use will be lower in the early years. Homes here means average household electricity, not heating, which in most Scottish homes is gas. The Scottish Parliament's researchers used Ofgem's "typical household" figure of 2,500 kWh, which gives higher home counts; we use Scotland's actual average. Scottish Government · National Records of Scotland

Proposed, in progress and stalled

31 schemes · 10,267 MW

Schemes from first announcement through to a lodged application, plus those under construction, refused or stalled. Most are large AI campuses still at pre-application, and together they would add many times today's operating capacity.

Chapelcross (CX Technology Campus)

1,000MW
CX Tech
Application lodgedGigawatt7 sourcesDumfries and Galloway
Validated 28 Sep 2026 · consultation open to 15 Nov 2026

i3 Industrial Park, Irvine

1,000MW
AI Pathfinder
StalledGigawatt5 sourcesNorth Ayrshire
Never entered planning

Edzell grid connection

800MW
Not disclosed
Grid queue onlyVery largeNeeds corroborationAngus
Grid queue

Auchtertool (Stoic Cato)

600MW
ILI Group
Application lodgedVery large5 sourcesFife
PPP validated 21 May 2026 · pending

Blackdog

600MW
Ashfield Land
AnnouncedVery large5 sourcesAberdeenshire
No data centre application on the council portal

Killellan, Dunoon

600MW
Argyll Data Development
StalledVery large6 sourcesArgyll and Bute
Small scheme approved · main plan reported stalled

Hurlford (Stoic Rufus)

540MW
ILI Group
Pre-applicationVery large5 sourcesEast Ayrshire
PAN done · no visible progress

Plains (Drumshangie)

500MW
Apatura
Pre-applicationVery large3 sourcesNorth Lanarkshire
PAN done

Easterhouse grid connection

500MW
Not disclosed
Grid queue onlyVery largeNeeds corroborationGlasgow
Grid queue

North Lanrigg Farm (Stoic Aurelius)

400MW
ILI Group
Pre-applicationVery large4 sourcesNorth Lanarkshire
PAN accepted Sep 2025 · EIA screening withdrawn 8 Oct 2026

Clydebridge grid connection

360MW
Not disclosed
Grid queue onlyVery largeNeeds corroborationSouth Lanarkshire
Grid queue

Glenbervie, Larbert

300MW
Apatura
Application lodgedVery large7 sourcesFalkirk
Hearing held 16 Sep 2026 · decision pending

Stainrigg Mains, Coldstream

300MW
Apatura
Pre-applicationVery large3 sourcesScottish Borders
PAN done · awaiting application

Westerhill, Bishopbriggs

300MW
Apatura
Pre-applicationVery large5 sourcesEast Dunbartonshire
PAN done · EIA required · awaiting application

Ravenscraig West

275MW
Apatura
Pre-applicationVery large6 sourcesNorth Lanarkshire
PAN done · awaiting application

Ravenscraig East

275MW
Apatura
Pre-applicationVery large6 sourcesNorth Lanarkshire
PAN done · awaiting application

Freeport West Lothian

250MW
Apatura
Pre-applicationVery large3 sourcesWest Lothian
PAN done · no further progress

Southside Data Centre, Longformacus

225MW
Sunlaws Development Co.
Pre-applicationLarge5 sourcesScottish Borders
Pre-application events held Jun 2026

South Gyle (former RBS HQ)

212MW
Shelborn
Refused / appealLarge6 sourcesCity of Edinburgh
Refused 9 Feb 2026 · appeal PPA-230-2794

Wester Hermiston

200MW
Apatura
Pre-applicationLarge4 sourcesCity of Edinburgh
PAN done · awaiting application

Creoch Farm, Ochiltree

200MW
Apatura
Pre-applicationLarge3 sourcesEast Ayrshire
EIA screening requested · awaiting application

Cockenzie (former coal store)

200MW
East Lothian Council & SDCL
AnnouncedLarge3 sourcesEast Lothian
Not yet in planning

Inchinan grid connection

180MW
Not disclosed
Grid queue onlyLargeNeeds corroborationRenfrewshire
Grid queue

Jawcraig grid connection

180MW
Not disclosed
Grid queue onlyLargeNeeds corroborationFalkirk
Grid queue

Former IBM site, Spango Valley

150MW
Slate Islands Development
Application lodgedLarge5 sourcesInverclyde
PPP submitted Sep 2026

DataVita DV4, Lancaster Road

120MW
DataVita
Application lodgedLarge6 sourcesNorth Lanarkshire
PPP submitted Sep 2026

DataVita DV3

—MW n/a
DataVita
Under constructionSize unknown5 sourcesNorth Lanarkshire
PPP permitted 9 Jan 2026 · under construction

DataVita DV6, South Lanridge Farm

—MW n/a
DataVita
Pre-applicationSize unknown2 sourcesNorth Lanarkshire
PAN accepted Jan 2026

Haspielaw

—MW n/a
Apatura
Pre-applicationSize unknown2 sourcesSouth Lanarkshire
EIA screening: EIA required (25 Jun 2025)

Hunterston Estate

—MW n/a
Eneus Energy
Pre-applicationSize unknown4 sourcesNorth Ayrshire
PAN published · EIA scoping

West Barns Mains, Dunbar

—MW n/a
Thistle Sands Data
Pre-applicationSize unknown4 sourcesEast Lothian
EIA screening requested Oct 2025

Operating

16 sites · 36.4 MW known

Data centres running in Scotland today, mostly colocation, bank and research sites in the Central Belt, Aberdeen and Dundee. Most are small; the largest, DataVita DV1 at Chapelhall, is about 24MW.

DataVita DV1

24MW
DataVita
OperatingMedium5 sourcesNorth Lanarkshire
Operating · expanding toward 40MW

Pulsant SC-1, South Gyle

3.4MW
Pulsant
OperatingSmall2 sourcesCity of Edinburgh
Operating

Pulsant SC-2, Bankhead Medway

2.16MW
Pulsant
OperatingSmall2 sourcesCity of Edinburgh
Operating

Brightsolid Aberdeen

2MW
Brightsolid
OperatingSmall4 sourcesAberdeen City
Operating

Brightsolid Dundee

1.5MW
Brightsolid
OperatingSmall3 sourcesDundee City
Operating

Pulsant SC-3, Newbridge

1.3MW
Pulsant
OperatingSmall2 sourcesCity of Edinburgh
Operating

DataVita DV2, Bothwell Street

1MW
DataVita
OperatingSmallNeeds corroborationGlasgow
Operating

iomart Glasgow DC1

1MW
iomart
OperatingSmall4 sourcesGlasgow
Operating

DataVita Fortis

—MW n/a
DataVita
OperatingSize unknownNeeds corroborationNorth Lanarkshire
Operating

Atos / Asanti Livingston

—MW n/a
Atos
OperatingSize unknown4 sourcesWest Lothian
Operating

Asanti Hamilton

—MW n/a
Asanti
OperatingSize unknown4 sourcesSouth Lanarkshire
Operating

IFB Union Street

—MW n/a
IFB
OperatingSize unknown3 sourcesAberdeen City
Operating

Lumen Glasgow

—MW n/a
Lumen
OperatingSize unknownNeeds corroborationGlasgow
Operating (per APRS)

NatWest E4 data centre, Macmerry

—MW n/a
NatWest Group
OperatingSize unknownNeeds corroborationEast Lothian
Operating (council records to 2025)

RBS data centre, Melville Gate

—MW n/a
NatWest Group
OperatingSize unknownNeeds corroborationMidlothian
Operating (council records to 2021)

Advanced Computing Facility (EPCC)

—MW n/a
University of Edinburgh (EPCC)
OperatingSize unknown3 sourcesMidlothian
Operating · national supercomputer planned

Planning and policy timeline

  1. Coming up
  2. Protest march against data centres planned in Edinburgh. Deadline News
  3. Consultation on Chapelcross closes (council record; campaigners had quoted 29 Oct). APRS
  4. Holyrood inquiry's call for views closes. Scottish Parliament
  5. National planning guidance for data centres expected. Data Centre Review
  6. What's happened
  7. Holyrood committees open an inquiry into hyperscale data centres. Call for views runs 7 Oct – 15 Nov. Scottish Parliament · Data Centre Review
  8. ILI Group withdraws its EIA screening request for the 400MW North Lanrigg (Aurelius) site. North Lanarkshire Council
  9. Dumfries and Galloway Council validates the 1GW Chapelcross application. DatacenterDynamics · Resultsense
  10. NESO tells Holyrood 28 data centres totalling 8.86GW are seeking grid connections in Scotland. NESO via Scottish Parliament
  11. MSPs reject an outright ban and back a pause of up to 12 months on decisions while guidance is drafted. Falkirk holds the Larbert hearing. Resultsense · Scottish Parliament
  12. EIA Direction makes environmental assessments mandatory for data centres over 50MW. Scottish Government
  13. DataVita files DV4 (about 120MW, £849.6m) with North Lanarkshire Council. DataVita · Data Centre Review
  14. DataVita secures £300m debt with a £202m National Wealth Fund guarantee. DataVita · The Register
  15. Ministers require councils to notify them within seven days of any data centre application over 50MW. Scottish Government
  16. ILI Group lodges a 600MW application at Auchtertool, Fife. Data Centre Review · DatacenterDynamics
  17. Edinburgh refuses the South Gyle scheme as not a green data centre under NPF4. The developer appeals. Data Centre Review · Scottish Government DPEA
  18. Lanarkshire named Scotland's first AI Growth Zone, built around DataVita's Chapelhall campus with CoreWeave. North Lanarkshire Council · Data Centre Review · techUK

How sources are graded

Each entry lists every source we used, labelled by who published it. An entry counts as corroborated when at least two different publishers report it and at least one of them is not a campaign group or a commercial directory.

GovernmentScottish or UK Government, Parliament, the planning appeals division (DPEA), NESO
CouncilLocal authority planning portal records, news or committee papers. Planning records were searched on each council's portal for "data centre" on 18 Oct 2026.
NoticeStatutory planning notices published in local papers
OperatorThe operator's or developer's own website or press release
NewsNewspapers, broadcasters and trade press
CampaignCampaign groups and petitions, including the APRS tracker
DirectoryCommercial data centre listings and property agents

Some news sites block automated link checks, but every link here was found through search and checked on 18 Oct 2026; none returned "not found".