East Lothian

West Barns Mains, Dunbar

Thistle Sands Data
Pre-application4 sourcesCapacity not publishedSize unknown
Where it stands4 independent sources
  1. Announced
  2. Proposal notice
  3. Application
  4. Decision
  5. Built

EIA screening 25/00008/SCR lodged 07 Oct 2025. A full application can follow 12 weeks after a notice. Decisions on data centres of 50 MW or more are currently paused for up to 12 months while national guidance is drafted.

Have your say · council applicationNo application to comment on yet. At proposal stage, comments go to the developer's public events.Council record 25/00008/SCR ↗How to have your say
Have your say · petition4,575 signaturesOppose the building of a hyperscale data centre in Dunbar ↗Signing a petition does not lodge an official objection with the council. Only comments made on the planning application count in the decision.
SizeNot publishedSize unknownSite about 60.8 ha
Surroundings
  • Nearest building 9 m · 776 within 500 m
  • 2% of the site in a surface water flood zone
  • Ancient woodland 116 m away
See the map
Public responseNo council comments published yet. Petition: 4,575 signatures.
How the flags work

Red: nearest building within 100 m, 10% or more of the site in a flood zone, or a designation overlapping the site. Amber: building within 500 m, any flood-zone overlap, or a designation within 500 m. Green: none of these. Measured from the council's application site; buildings from OpenStreetMap, flood zones from SEPA, designations from NatureScot and Historic Environment Scotland.

Overview

"Green energy data centre and community renewable heat hub" on a 62.5ha site. The council record names Thistle Sands Data Limited as applicant. Capacity not published.

The developer's case

No project website, public statement or published figures from the developer found yet. Spotted one? Use Report incorrect data at the top of the page.

The objectors' case

Objectors say the scheme would change the character of a historic coastal town and harm its landscape and local ecology. change.org petition

petition signatures4,575

Petitions and campaigns

The opening lines summarise in our own words how objectors present their case. Campaign claims get the same checks as the developer's figures. Petition signatures are not verified as local and are not formal objections to the council.

Site and surroundings

Loading map layers…
Site centreResidentialIndustrial / commercialWoodland River floodSurface water floodCoastal flood SSSI / SAC / SPAAncient woodlandHeritage designation Listed buildingSchool, care or healthPower line250 m · 500 m · 1 km from the site centre

See the exact red-line boundary on the council's map ↗ · Building counts and flood shares are measured from the council's application boundary; the rings are drawn from the site centre. Map data © OpenStreetMap contributors, available under the Open Database Licence. Flood maps © SEPA; designations © NatureScot and © Historic Environment Scotland; all under the Open Government Licence v3.0. Contains OS data © Crown copyright and database right 2026.

Planning

Where it stands: EIA screening requested Oct 2025.

  1. Proposal of application noticeNot found on the council portal
  2. EIA screening or scoping25/00008/SCR · Status not read (portal rate-limited) · 07 Oct 2025
  3. Planning application lodgedNot yet lodged
  4. Council decision
Site locationCentre of the application site for 25/00008/SCR, about 60.8 ha. Grid reference E 367413 N 677069.
See the red-line boundary on East Lothian Council's map ↗
Council planning record · East Lothian Council
ReferenceTypeStatusDateApplicant
25/00008/SCREIA screening, West Barns MainsStatus not read (portal rate-limited)07 Oct 2025Thistle Sands Data Limited

Rules that apply

  • Over 50MW, the council must notify Scottish Ministers within seven days of validating an application (in force since 17 Aug 2026). Scottish Government
  • Over 50MW, an Environmental Impact Assessment is now mandatory (Direction of 16 Sep 2026), including for applications already in the system. Scottish Government
  • On 16 Sep 2026 MSPs backed pausing planning decisions on large data centres for up to 12 months while national guidance is drafted, expected by December 2026. Resultsense
  • For a major development, the developer must lodge a proposal of application notice and hold at least two public events, and cannot submit the application until 12 weeks after the notice.
  • No capacity has been published. The 50MW rules above apply if the scheme exceeds 50MW.

Search the East Lothian planning portal for the latest documents, consultee responses and public comments.

Sources