Overview
One of ILI's three Stoics sites. ILI says each has a grid connection and land rights.
The developer's case
Part of ILI's three-site 'Stoics' network (Rufus), presented as run on renewable power. ILI Group
Developer website ↗
Jobs in context
Permanent jobs claimedNone published
At the 1.6 per MW study averageabout 864for 540 MW
Industry modeltechUK, based on older, smaller sites8.5
Planned UK sitesVerdant study of 20 schemes, 20261.6
QTS Cambois, Northumberland720 MW, about 400 jobs0.56
Permanent jobs per megawatt of capacity.
Construction jobs are real but temporary. Figures for "job-years", "jobs supported" or "indirect" jobs count work elsewhere in the economy, not people on site. The per-MW measure comes from the think tank Verdant; techUK says it misses jobs supported outside the site, and the UK Government calls it misleading. The Next Web Resultsense
Site and design
| Land | Farmland (Purroch Farm) |
|---|
The opening lines summarise in our own words how the developer presents the scheme. Items marked Claim are the developer's own figures, not independently checked.
The objectors' case
The opening lines summarise in our own words how objectors present their case. Campaign claims get the same checks as the developer's figures. Petition signatures are not verified as local and are not formal objections to the council.
Planning
Where it stands: PAN done · no visible progress.
Proposal of application notice25/0008/PREAPP · Approved with Conditions · 25 Nov 2025
EIA screening or scopingNot found on the council portal
Planning application lodgedNot yet lodged
Council decision
Site location: no site boundary is published on the council's planning map for this application. The position shown is approximate.
Council planning record · East Ayrshire Council
| Reference | Type | Status | Date | Applicant |
|---|
| 25/0008/PREAPP | Proposal of application notice, Purroch Farm | Approved with Conditions | 25 Nov 2025 | ILI Rufus Limited |
Rules that apply
- Over 50MW, the council must notify Scottish Ministers within seven days of validating an application (in force since 17 Aug 2026). Scottish Government
- Over 50MW, an Environmental Impact Assessment is now mandatory (Direction of 16 Sep 2026), including for applications already in the system. Scottish Government
- On 16 Sep 2026 MSPs backed pausing planning decisions on large data centres for up to 12 months while national guidance is drafted, expected by December 2026. Resultsense
- For a major development, the developer must lodge a proposal of application notice and hold at least two public events, and cannot submit the application until 12 weeks after the notice.
Search the East Ayrshire planning portal for the latest documents, consultee responses and public comments.
Public response
1against
0in support
0neutral
100% of comments that took a side were against. From the public comments tab of 25/0008/PREAPP, read 19 Oct 2026. This council publishes the counts but not the comment text, so what people wrote cannot be analysed.