North Lanarkshire

North Lanrigg Farm (Stoic Aurelius)

Pre-application4 sources400 MWVery large
Where it stands4 independent sources
  1. Announced
  2. Proposal notice
  3. Application
  4. Decision
  5. Built

Proposal notice 25/00989/PAN lodged 22 Sep 2025. A full application can follow 12 weeks after a notice. Decisions on data centres of 50 MW or more are currently paused for up to 12 months while national guidance is drafted.

Have your say · council applicationNo application to comment on yet. At proposal stage, comments go to the developer's public events.Council record 25/00989/PAN ↗How to have your say
Size400 MWVery large10% of Scotland's winter peak demandSite about 46 ha
Surroundings
  • Nearest building 17 m · 77 within 500 m
  • 4% of the site in a surface water flood zone
  • Ancient woodland 384 m away
See the map
Public responseNo public comments published yet.
How the flags work

Red: nearest building within 100 m, 10% or more of the site in a flood zone, or a designation overlapping the site. Amber: building within 500 m, any flood-zone overlap, or a designation within 500 m. Green: none of these. Measured from the council's application site; buildings from OpenStreetMap, flood zones from SEPA, designations from NatureScot and Historic Environment Scotland.

Overview

The third of ILI's Stoics sites. ILI withdrew its EIA screening request on 8 Oct 2026.

The developer's case

Part of ILI's three-site 'Stoics' network (Aurelius), presented as run on renewable power. ILI Group

Developer website ↗

Jobs in context

Permanent jobs claimedNone published
At the 1.6 per MW study averageabout 640for 400 MW
Industry modeltechUK, based on older, smaller sites8.5
Planned UK sitesVerdant study of 20 schemes, 20261.6
QTS Cambois, Northumberland720 MW, about 400 jobs0.56

Permanent jobs per megawatt of capacity.

Construction jobs are real but temporary. Figures for "job-years", "jobs supported" or "indirect" jobs count work elsewhere in the economy, not people on site. The per-MW measure comes from the think tank Verdant; techUK says it misses jobs supported outside the site, and the UK Government calls it misleading. The Next Web Resultsense

The opening lines summarise in our own words how the developer presents the scheme. Items marked Claim are the developer's own figures, not independently checked.

The objectors' case

No organised objection or formal objections found yet. Know of a campaign group? Use Report incorrect data at the top of the page.

Site and surroundings

Loading map layers…
Site centreResidentialIndustrial / commercialWoodland River floodSurface water floodCoastal flood SSSI / SAC / SPAAncient woodlandHeritage designation Listed buildingSchool, care or healthPower line250 m · 500 m · 1 km from the site centre

See the exact red-line boundary on the council's map ↗ · Building counts and flood shares are measured from the council's application boundary; the rings are drawn from the site centre. Map data © OpenStreetMap contributors, available under the Open Database Licence. Flood maps © SEPA; designations © NatureScot and © Historic Environment Scotland; all under the Open Government Licence v3.0. Contains OS data © Crown copyright and database right 2026.

Planning

Where it stands: PAN accepted Sep 2025 · EIA screening withdrawn 8 Oct 2026.

  1. Proposal of application notice25/00989/PAN · PAN accepted (comments issued) · 22 Sep 2025
  2. EIA screening or scoping26/00595/EIASCR · Application Withdrawn · 08 Oct 2026
  3. Planning application lodgedNot yet lodged
  4. Council decision
Site locationCentre of the application site for 25/00989/PAN, about 46 ha. Grid reference E 279796 N 661361.
See the red-line boundary on North Lanarkshire Council's map ↗
Council planning record · North Lanarkshire Council
ReferenceTypeStatusDateApplicant
25/00989/PANProposal of application noticePAN accepted (comments issued)22 Sep 2025
26/00595/EIASCREIA screening requestApplication Withdrawn08 Oct 2026

Rules that apply

  • Over 50MW, the council must notify Scottish Ministers within seven days of validating an application (in force since 17 Aug 2026). Scottish Government
  • Over 50MW, an Environmental Impact Assessment is now mandatory (Direction of 16 Sep 2026), including for applications already in the system. Scottish Government
  • On 16 Sep 2026 MSPs backed pausing planning decisions on large data centres for up to 12 months while national guidance is drafted, expected by December 2026. Resultsense
  • For a major development, the developer must lodge a proposal of application notice and hold at least two public events, and cannot submit the application until 12 weeks after the notice.

Search the North Lanarkshire planning portal for the latest documents, consultee responses and public comments.