Falkirk

Glenbervie, Larbert

Application lodged7 sources300 MWVery large
Where it stands7 independent sources
  1. Announced
  2. Proposal notice
  3. Application
  4. Decision
  5. Built

Application P/26/0237/FUL lodged 04 Jun 2026; awaiting the council's decision. Decisions on data centres of 50 MW or more are paused for up to 12 months while national guidance is drafted (expected by December 2026).

Have your say · council applicationFormal comment period ended 24 Aug 2026. Late comments are at the council's discretion.Council record P/26/0237/FUL ↗How to have your say
Size300 MWVery large7.5% of Scotland's winter peak demandSite about 18.8 ha
Surroundings
  • Nearest building 19 m · 926 within 500 m
  • 3% of the site in a surface water flood zone
  • Ancient woodland 39 m away
See the map
Public response7,113 against · 83 forOn P/26/0237/FUL
How the flags work

Red: nearest building within 100 m, 10% or more of the site in a flood zone, or a designation overlapping the site. Amber: building within 500 m, any flood-zone overlap, or a designation within 500 m. Green: none of these. Measured from the council's application site; buildings from OpenStreetMap, flood zones from SEPA, designations from NatureScot and Historic Environment Scotland.

Overview

Full application P/26/0237/FUL on 55 acres off Bellsdyke Road, moved here from an earlier site at Plean. 7,284 representations, 7,166 of them objections. Councillors questioned 200 diesel backup generators, noise and tree loss.

The developer's case

Presents the campus as a green hyperscale project on business-allocated land, arguing that demand from AI is rising fast and that the investment and jobs will go elsewhere if Scotland does not act now. Apatura consultation site

Consultation website ↗Claimed benefits ↗

Consultation events

  • 28 Oct 2025 Public consultation meeting, Glenbervie House
  • 27 Nov 2025 Public consultation meeting, Glenbervie House
  • 28 Oct 2026 Webinar for Bellsdyke and Stirling Road residents Upcoming
  • 29 Oct 2026 Larbert community webinar Upcoming

Comments made at these events go to the developer. They are not formal comments to the council, which can only be made once an application is lodged.

Claim Construction: More than 5,000 jobs a year during construction (at filing) FutureScot

Jobs in context

Permanent jobs claimed297
At the 1.6 per MW study averageabout 480for 300 MW
Claimed jobs per MW0.99
This scheme's claim0.99
Industry modeltechUK, based on older, smaller sites8.5
Planned UK sitesVerdant study of 20 schemes, 20261.6
QTS Cambois, Northumberland720 MW, about 400 jobs0.56

Permanent jobs per megawatt of capacity. This claim is below the study's average for planned sites.

Construction jobs are real but temporary. Figures for "job-years", "jobs supported" or "indirect" jobs count work elsewhere in the economy, not people on site. The per-MW measure comes from the think tank Verdant; techUK says it misses jobs supported outside the site, and the UK Government calls it misleading. The Next Web Resultsense

Claimed benefits

InvestmentDeveloper estimate About £1bn (£2.3bn on the consultation website) FutureScot
Local spendModelled estimate £215m of construction spend retained in Falkirk Apatura consultation site
Economic value (GVA)Modelled estimate £765m during construction; £306m a year once operational Apatura consultation site
Community benefitPromise only £1.8m a year Resultsense
Skills and trainingPromise only Training through partnerships with colleges and universities (no detail yet) Apatura consultation site
  • Developer estimate The developer's own figure for what it plans to spend. Not a commitment.
  • Modelled estimate Comes from an economic model the developer paid for. Not checked independently.
  • Promise only Not yet written into a legal agreement (Section 75) or a planning condition, so it cannot be enforced.
  • Secured Written into a signed legal agreement or planning condition.

None of these benefits is secured yet for any scheme we track. GVA (gross value added) is the economic output a scheme is modelled to add.

Site and design

LandDisputed Disputed: disused business land or former farmland DatacenterDynamics Resultsense
Power supplyClaim Grid via Denny substation, linked battery site FutureScot
Backup power200 diesel generators Resultsense
Worth knowing: Figures have shifted: 1,300 long-term jobs at filing, 297 on-site jobs later; nearly £1bn of investment at filing, £2.3bn on the consultation site. Its benefits page also gives two different apprenticeship levy figures (£339,000 and £583,000) in the same line.

The opening lines summarise in our own words how the developer presents the scheme. Items marked Claim are the developer's own figures, not independently checked.

The objectors' case

More than 7,000 objections were lodged. At the hearing, councillors questioned the 200 diesel backup generators, noise and the loss of trees, and the site's status as business land is disputed. Resultsense DatacenterDynamics

formal objections7,113

The opening lines summarise in our own words how objectors present their case. Campaign claims get the same checks as the developer's figures. Petition signatures are not verified as local and are not formal objections to the council.

Site and surroundings

Loading map layers…
Site centreResidentialIndustrial / commercialWoodland River floodSurface water floodCoastal flood SSSI / SAC / SPAAncient woodlandHeritage designation Listed buildingSchool, care or healthPower line250 m · 500 m · 1 km from the site centre

See the exact red-line boundary on the council's map ↗ · Building counts and flood shares are measured from the council's application boundary; the rings are drawn from the site centre. Map data © OpenStreetMap contributors, available under the Open Database Licence. Flood maps © SEPA; designations © NatureScot and © Historic Environment Scotland; all under the Open Government Licence v3.0. Contains OS data © Crown copyright and database right 2026.

Planning

Where it stands: Hearing held 16 Sep 2026 · decision pending.

  1. Proposal of application noticeNot listed separately
  2. EIA screening or scopingNot listed separately
  3. Planning application lodgedP/26/0237/FUL · Awaiting decision · 04 Jun 2026
  4. Council decisionAwaiting decision
Site locationCentre of the application site for P/26/0237/FUL, about 18.8 ha. Grid reference E 285201 N 683661.
See the red-line boundary on Falkirk Council's map ↗
Council planning record · Falkirk Council
ReferenceTypeStatusDateApplicant
P/26/0237/FULFull planning applicationAwaiting decision04 Jun 2026Apatura DC Project 5 Ltd

Rules that apply

  • Over 50MW, the council must notify Scottish Ministers within seven days of validating an application (in force since 17 Aug 2026). Scottish Government
  • Over 50MW, an Environmental Impact Assessment is now mandatory (Direction of 16 Sep 2026), including for applications already in the system. Scottish Government
  • On 16 Sep 2026 MSPs backed pausing planning decisions on large data centres for up to 12 months while national guidance is drafted, expected by December 2026. Resultsense

Search the Falkirk planning portal for the latest documents, consultee responses and public comments.

Public response

7,113against
83in support
27neutral
159neighbours notified

99% of comments that took a side were against. From the public comments tab of P/26/0237/FUL, read 19 Oct 2026. This council publishes the counts but not the comment text, so what people wrote cannot be analysed.

Concerns reported

Case made for it

  • About 500 jobs during delivery; keeps AI investment in Scotland Resultsense

Issues as reported in news and campaign coverage, not a count of comments.

Statutory consultees

26 consulted, 22 responded. Including: Scottish Water · Scottish Government · National Architectural Liaison Support & Development Officer · Scottish Water (EIA Consultations) · NHS Forth Valley · Environmental Protection Unit · Roads Development Unit · Emergency Planning Unit · Falkirk Council Climate Change and Energy Team · HSE PADHI+