North Lanarkshire

DataVita DV6, South Lanridge Farm

Pre-application2 sourcesCapacity not publishedSize unknown
Where it stands2 independent sources
  1. Announced
  2. Proposal notice
  3. Application
  4. Decision
  5. Built

Proposal notice 25/01328/PAN lodged 29 Jan 2026. A full application can follow 12 weeks after a notice. Decisions on data centres of 50 MW or more are currently paused for up to 12 months while national guidance is drafted.

Have your say · council applicationNo application to comment on yet. At proposal stage, comments go to the developer's public events.Council record 25/01328/PAN ↗How to have your say
SizeNot publishedSize unknownSite about 111.6 ha
Surroundings
  • Nearest building 5 m · 143 within 500 m
  • 3% of the site in a river flood zone
  • Ancient woodland overlaps the site
See the map
Public responseNo public comments published yet.
How the flags work

Red: nearest building within 100 m, 10% or more of the site in a flood zone, or a designation overlapping the site. Amber: building within 500 m, any flood-zone overlap, or a designation within 500 m. Green: none of these. Measured from the council's application site; buildings from OpenStreetMap, flood zones from SEPA, designations from NatureScot and Historic Environment Scotland.

Overview

APRS says DV4 and DV6 together form the AI Growth Zone's 500MW target. The council record places the site at Linrigg Road, Newhouse, not at the Chapelhall campus.

The developer's case

We have not found a project website or public statement from the developer beyond what is listed below.

DataVita website ↗

Site and design

LandFarmland (South Lanridge Farm)

Items marked Claim are the developer's own figures, not independently checked.

The objectors' case

No organised objection or formal objections found yet. Know of a campaign group? Use Report incorrect data at the top of the page.

Site and surroundings

Loading map layers…
Site centreResidentialIndustrial / commercialWoodland River floodSurface water floodCoastal flood SSSI / SAC / SPAAncient woodlandHeritage designation Listed buildingSchool, care or healthPower line250 m · 500 m · 1 km from the site centre

See the exact red-line boundary on the council's map ↗ · Building counts and flood shares are measured from the council's application boundary; the rings are drawn from the site centre. Map data © OpenStreetMap contributors, available under the Open Database Licence. Flood maps © SEPA; designations © NatureScot and © Historic Environment Scotland; all under the Open Government Licence v3.0. Contains OS data © Crown copyright and database right 2026.

Planning

Where it stands: PAN accepted Jan 2026.

  1. Proposal of application notice25/01328/PAN · PAN accepted (comments issued) · 29 Jan 2026
  2. EIA screening or scopingNot found on the council portal
  3. Planning application lodgedNot yet lodged
  4. Council decision
Site locationCentre of the application site for 25/01328/PAN, about 111.6 ha. Grid reference E 280393 N 661079.
See the red-line boundary on North Lanarkshire Council's map ↗
Council planning record · North Lanarkshire Council
ReferenceTypeStatusDateApplicant
25/01328/PANProposal of application notice, South Lanridge FarmPAN accepted (comments issued)29 Jan 2026

Rules that apply

  • Over 50MW, the council must notify Scottish Ministers within seven days of validating an application (in force since 17 Aug 2026). Scottish Government
  • Over 50MW, an Environmental Impact Assessment is now mandatory (Direction of 16 Sep 2026), including for applications already in the system. Scottish Government
  • On 16 Sep 2026 MSPs backed pausing planning decisions on large data centres for up to 12 months while national guidance is drafted, expected by December 2026. Resultsense
  • For a major development, the developer must lodge a proposal of application notice and hold at least two public events, and cannot submit the application until 12 weeks after the notice.
  • No capacity has been published. The 50MW rules above apply if the scheme exceeds 50MW.

Search the North Lanarkshire planning portal for the latest documents, consultee responses and public comments.